Electricity supply from L.Turkana power plant cut off indefinitely

Kenya Power has warned of a pending power shortfall.

In Summary

• This has raised fears of a power shortage and rationing in the country in the coming days following the incident where four towers collapsed in the Longonot area of Mai Mahiu.

• Already, engineers from the power company and the Kenya Electricity Transmission Company (KETRACO) have embarked on repairing the damaged sections.

Staff from Kenya Power Company and Kenya Electricity Transmission Company move in (on 22-12-21) to repair one of the four electricity towers along that 220kv Loyangalani-Suswa line that clashed in Longonot area of Naivasha cutting off electricity power supply to the national grid.
Staff from Kenya Power Company and Kenya Electricity Transmission Company move in (on 22-12-21) to repair one of the four electricity towers along that 220kv Loyangalani-Suswa line that clashed in Longonot area of Naivasha cutting off electricity power supply to the national grid.
Image: GEORGE MURAGE

Electricity supply from the 300MW Lake Turkana Wind Power Plant has been cut off indefinitely after a section of the 220kV Loiyangalani-Suswa electricity line clashed.

This has raised fears of a power shortage and rationing in the country in the coming days following the incident where four towers collapsed in the Longonot area of Mai Mahiu.

Already, Kenya Power company has warned of a pending power shortfall as its engineers moved in to access the damage.   

Already, engineers from the power company and the Kenya Electricity Transmission Company (KETRACO) have embarked on repairing the damaged sections.

Following the incident, Kenya Power issued a statement to assure electricity consumers that normalcy would be restored in the coming days.

The company noted that the incident had led to the switching off of the Turkana power plant that is connected to the Suswa substation resulting in a generation shortfall.

“Kenya Power engineers are working closely with other agencies to reconstruct the affected section and restore power supply in the shortest time possible,” said the company.

This came as families living along the powerline raised their concern after a section of the high voltage cables fell in their compounds in Longonot village.

According to John Njenga, the first tower clashed over the weekend before the other three followed suit, raising fear and anxiety in the area.

He noted that they had in the past requested KETRACO to relocate families near the power line but their pleas fell on deaf ears before the accident occurred.

“It's by God’s grace that the power line fell on the cowshed after one of the nearby tower lines clashed and we hope this will be fully resolved in the coming days,” he said.

Njenga said that there were fears that other towers along the line could collapse in the coming days due to the strong winds in the area.

Another resident David Waigi said that the blame lay with KETRACO which failed to give ample space along the power line during its construction two years ago.

He said that families living near the power line were ready to move out if the power transmission company compensated them.

“Already four electricity towers have collapsed and there are fears that more could clash leading to loss of life and property in this area,” he said.

The incident has raised concern over the quality of works on the powerline with fingers pointing at the contractor involved in the project for the collapse of the power towers.

Edited by D Tarus

WATCH: The latest videos from the Star