Gathungu flags major delays in multibillion shilling dam projects
At the heart of the audit queries is the Sh19.99 billion Soin-Koru dam water project in Kericho and Kisumu counties.
by MOSES OGADA
Audio By Vocalize
Auditor-General Nancy Gathungu/FILE
National Water Harvesting and Storage Authority has
come under scrutiny after Auditor-General Nancy Gathungu flagged significant
delays in the implementation of multi-billion-shilling dam projects.
In her report on the authority's accounts for the
financial year ended June 30, 2025, Gathungu raised concerns over the slow
progress of the dams.
At the heart of the audit queries is the Sh19.99
billion Soin-Koru dam water project in Kericho and
Kisumu counties.
The Umaa dam in Kitui has
also been flagged, with the auditor warning that the setbacks could deny the
targeted communities the intended benefits.
She further said that there may be no value for money for the
billions of shillings committed to the projects.
The audit has cast doubt on the pace at which the
government is pursuing the water storage agenda.
The authority itself listed the dams among flagship
projects expected to boost water security, irrigation and flood control across
the country.
For Koru-Soin, according to the report, the
authority signed a contract with a joint venture contractor on May 11, 2022,
with an expected completion date of August 27 next year.
However, a review by auditors found little
meaningful progress on the ground.
“The contractor is not on site,” Gathungu said, adding that several critical components of the
project had either not commenced or remained incomplete.
Among the works yet to begin were excavation
activities, seepage control systems, grouting, diaphragm walls, relief wells
and laboratory testing.
Construction of the planned 54-metre-high zoned
earth-rock fill dam had also not started.
The audit further established that intake towers,
diversion culverts, road infrastructure, water abstraction facilities,
hydropower-related works, access bridges, security installations and river
training activities had not been undertaken.
The only notable progress was on the side-channel
spillway, which auditors estimated to be about 15 per cent complete.
The findings raise fresh questions about the fate
of one of the largest water storage projects, which is expected to support
irrigation, domestic water supply and power generation in the Lake Victoria
region.
On the Sh1.96 billion Umaa dam which has also been flagged over slow
implementation, the contract was awarded in December 2023.
It was handed to a joint venture between Vanqo
Roads and Engineering Ltd and a Chinese firm, with completion expected by
January 2.
Although the project has attracted substantial
public investment, the audit found that progress remained below expectations.
Records show that the authority had already paid
Sh284.7 million, while additional certified claims worth Sh548.5 million were
yet to be settled.
A physical inspection conducted in November last year revealed that while the contractor was present on
site, no active construction work was underway.
Consultants were also absent during the audit
visit, the report shows.
The audit said that
some components, including the downstream cofferdam, grouting works, pressure
tests, inlet chambers and trenches, had been completed.
However, major elements such as rehabilitation of
the previous water treatment plant, construction of the sedimentation basin,
installation of an elevated water tank, completion of the spillway and fencing
of the project site had not been undertaken.
Auditors further warned that pipes procured by a
previous contractor had been left exposed to direct sunlight and risked
deterioration.
Overall, the project was estimated to be only 57
per cent complete.
“In the circumstances, delays in the project
implementation may hinder the timely realisation of the intended benefits to
the community,” Gathungu said.
The concerns over the dams come against the
backdrop of unresolved audit issues that the authority has carried forward from
previous financial years.
Several longstanding audit concerns, including land
without title deeds, uncollected rental revenue, arbitration claims arising
from the Peace Dam contract, irregular board composition and the slow
implementation of the Umaa dam project remained
unresolved.
The report says failure to address the issues
contravenes a National Treasury directive requiring government entities to
clear all audit queries raised in the 2021-22 and 2022-23 financial years.
Ironically, the authority's own leadership has
continued to cite the dams as among its key achievements and priorities.
In the report, the board said there had been ‘good
progress’ on the Muruny (Siyoi) dam project and
continued implementation of the Umaa dam project.
It also identified Umaa, Soin-Koru and Muruny
(Siyoi) among dam projects earmarked for continued funding.
This is premium content
Subscribe to Continue Reading
Help us continue bringing you unbiased news, in-depth investigations, and diverse perspectives. Your subscription keeps our mission alive and empowers us to provide high-quality, trustworthy journalism. Join us today to make a difference!