The report for the financial year ending June 30, 2025, shows the state-owned milk processor received raw milk grants totalling Sh3.9
billion over two years.
Of this, Sh1.5 billion was disbursed in the financial year 2023-24
and Sh2.4 billion in 2024-25 to support milk purchases from farmers during
periods of oversupply.
However, the Auditor General says records provided
during the audit indicate the money may already have been fully spent despite
the company still reflecting Sh3.17 billion as unutilised reserves.
“The statement reflects raw milk grant utilisation of
Sh730,753,000, leaving the balance of Sh3,169,247,000 as an unutilised grant as
at June 30, 2025,” Gathungu says in the report.
“However, payment records provided for audit show that
all the funds received by the company had been fully paid to farmers for milk
delivered to various company plants, which implies that the entire reserves
needed to have been utilised.”
Gathungu consequently questioned the existence and
accuracy of the reserve fund.
“In the circumstances, the accuracy and validity of the milk
mop-up reserve/fund of Sh3,169,247,000 could not be confirmed,” she said.
The Auditor General further noted that New KCC’s
financial position did not support the existence of the reserve.
According to the audit, the company reported cash and
cash equivalents amounting to Sh228.5 million by the close of the financial
year.
Even so, it also had bank overdrafts of Sh476.6 million,
leaving it with a negative cash position of about Sh248 million.
The report separately questioned how the company arrived
at the Sh730.7 million listed as utilised from the milk grant.
“Supporting documents on how the utilisation amount was
arrived at were not satisfactorily explained,” Gathungu said.
The audit also raised concerns over an unsupported
payment of Sh300 million back to the exchequer linked to emergency funds
advanced under Article 223 of the Constitution during the 2023-24 El Niño
period.
It had received Sh600 million in May 2024 to cushion
farmers and support milk mop-up activities following the El Niño effects.
However, Parliament later regularised only Sh300 million
through a supplementary budget, resulting in the recovery of the excess amount
from New KCC’s 2024-25 budget.
Despite this, management reportedly recognised the
entire Sh600 million in the milk mop-up reserve.
“The Constitution is silent on action to be taken on
funds disbursed under Article 223 of the Constitution and regularisation not
done by Parliament,” Gathungu said.
She added that justification for the refund was not
provided for audit review, meaning the regularity and propriety of the Sh300
million payment back to the Exchequer could not be confirmed.
The report further paints the picture of a financially
strained company despite receiving billions in state support.
New KCC posted a pre-tax loss of Sh974.6 million during
the year under review, while its current liabilities exceeded current assets by
Sh859.8 million, indicating negative working capital.
The company also incurred finance costs amounting to
Sh369.4 million, including interest expenses on loans and overdrafts exceeding
Sh368 million.
“These events or conditions indicate that a material
uncertainty exists that casts significant doubt on the company’s ability to
continue as a going concern,” Gathungu warned.
The Auditor General also faulted New KCC for
overspending beyond its actual revenues during the financial year under review.
The company had budgeted to receive Sh8.95 billion but
realised only Sh7.61 billion, resulting in a revenue shortfall of Sh1.33
billion.
Despite the lower revenues, the milk processor spent
Sh9.07 billion, exceeding actual receipts by Sh1.45 billion or 19 per cent.
“The under-realisation and over-utilisation affected the
planned activities and may have impacted negatively on service delivery to the
public,” the report states.
The audit further found that trade and other payables
stood at Sh3.97 billion, with Sh3.24 billion having remained unpaid for more
than 120 days.
“Failure to settle the debts as and when they fall due
may attract interest and operations if suppliers stop supplies due to
non-payment,” Gathungu cautioned.
Three construction projects at the Kericho sales depot, valued at Sh37.7 million and initiated in 2021, were also found to be incomplete
four years later, despite having been scheduled for completion within one year.
The audit further found that 570 out of New KCC’s 1,486
employees had overcommitted their salaries beyond the legal two-thirds
threshold, contrary to public service regulations.