logo
ADVERTISEMENT

Rironi–Nakuru Highway dualling set to begin under PPP model– CS Chirchir

He explained that the dualling project will stretch from Rironi to Nakuru, continue to Eldoret, and eventually extend to Malaba.

image
by SHARON MWENDE

News16 July 2025 - 13:39
ADVERTISEMENT

In Summary


  • The CS further revealed that the Ministry of Roads and Transport, through the Kenya National Highways Authority (KeNHA), is preparing a new procurement process to facilitate the works.
  • He said both the A8 and A8 South sections of the corridor will be covered under this plan.

Roads and Transport CS Davis Chirchir during a past meeting with the National Assembly Committee/ DAVIS CHIRCHIR/X
The government plans to begin dualization of the Rironi–Nakuru–Eldoret highway at the end of August under the Public-Private Partnership (PPP) model.

Speaking before the Senate on Wednesday, Roads and Transport Cabinet Secretary Davis Chirchir stated that the project will significantly ease congestion on the busy Northern Corridor, which links Nairobi to Western Kenya and beyond.

“We plan to undertake the dualling of the Rironi–Nakuru and Nakuru–Eldoret highways under the Public Private Partnership process,” Chirchir said.

“We have gotten a number of concession proponents, and they are currently going through the development phase. We expect to break ground before the end of August, all going well.”

He explained that the dualing project will stretch from Rironi to Nakuru, continue to Eldoret, and eventually extend to Malaba.

He clarified the route, saying:

“Just to remind ourselves… Rironi is where the current dualling ends and goes all the way to Nakuru, to Eldoret and all the way to Malaba.”

Road dualling is converting a single-lane road into a dual-carriageway to improve traffic flow and reduce congestion.

The CS further revealed that the Ministry of Roads and Transport, through the Kenya National Highways Authority (KeNHA), is preparing a new procurement process to facilitate the works.

He said both the A8 and A8 South sections of the corridor will be covered under this plan.

“We will do Rironi, Mai Mahiu, Naivasha as a bypass. It is called A8 South. So we'll do A8, which is Rironi, Naivasha, Nakuru, all the way to Mau Summit,” he said.

According to Chirchir, no contractor has been awarded yet.

The proposals are still undergoing evaluation under the PPP framework.

“As we speak, we do not have a contractor. They are currently being evaluated,” he noted.

On-site preparations have already begun, with technical teams conducting soil testing and other preliminary works, he said.

“When you drive on that road today, you will find some people drilling the road to check the profile of the geotechnical work in terms of the structure of the soils,” Chirchir said.

“We have given them some 10 days to finish that and give us the response so that if we were to award, we’ll then be able to answer the second question on who the contractors are.”

On June 11, 2025, while meeting with Nakuru leaders at the State House in Nairobi, President William Ruto stated that the road works would begin in August.

Ruto noted that the design work and other technical aspects of the project are almost complete before he breaks ground on it in two months.

"We have agreed with the contractors to speed up the project and complete it by 2027. If not, they should have done a substantial portion of it by that time," he said.

He explained that the Rironi-Mau Summit Road would consist of four lanes from Rironi to Naivasha town, as well as the Maai Mahiu-Naivasha road.

The President highlighted that the road will then be expanded to six lanes from Naivasha town to Nakuru City, in order to handle the high volume of traffic on the route adequately.

Related Articles

ADVERTISEMENT