Billions of shillings in taxpayers’ money remain
tied up in government projects that have dragged on for years, some dating back
to 2013.
A new report by Controller of Budget Margaret
Nyakang’o reveals a pattern in which slow-moving projects continue to receive
allocations in successive budgets despite minimal progress.
The review covering July–December 2025 cites
stalled projects across sectors, including diplomatic missions, trade
infrastructure, agriculture, maritime systems and aviation facilities.
Several state lodge refurbishments are among the
projects that have dragged on for years despite heavy spending.
Refurbishment of Eldoret State Lodge, launched in
2016, is only five per cent complete. Sagana State Lodge stands at 27 per cent
completion, Kisumu at 14 per cent and Kisii at just two per cent.
Works at Kakamega State Lodge, which began in 2015,
have also reached only two per cent completion.
“The delays highlight the critical need for
strategic planning and prioritisation to ensure timely project completion,”
Nyakang’o said.
President William Ruto and Treasury Cabinet Secretary John Mbadi have repeatedly urged government
agencies to complete ongoing projects before initiating new ones.
Parliament has raised similar concerns. The
National Assembly Budget Committee said that
although the 2026 Budget Policy Statement prioritises completing ongoing or
stalled projects, many remain delayed.
In the 2023-24 financial year alone, 24 ministries,
departments and agencies had stalled or delayed projects worth Sh38.24 billion,
with Sh7.9 billion already spent.
“It was noted that funds already spent on
non-functional projects are effectively sunk costs providing no services or
value for money,” MPs said in their report on the Budget Policy Statement.
Some of the most glaring cases involve renovation
projects at Kenya’s diplomatic missions abroad.
Renovation of government-owned properties in Dar es
Salaam and fencing of land allocated in Dodoma began in November 2016 but had
reached only 21 per cent completion by December last year. The project has already consumed about Sh122
million.
Similarly, renovation of government properties in
Addis Ababa, launched in July 2019 at an estimated cost of Sh500 million, had
reached only 13 per cent completion. By December last year, Sh65.9 million had already been spent.
Other diplomatic projects with minimal progress
include renovations of government properties in Lusaka and Kinshasa, both
standing at five per cent completion.
The purchase and renovation of the ambassador’s
residence in New York has reached only six per cent completion despite about
Sh4 billion already being spent on the works and related purchases.
The report further notes that some projects
remained active in development budgets but recorded no expenditure during the
six-month review period.
Economists have previously warned that stalled
projects create heavy fiscal burdens.
Jairus Kedogo and Oscar Ochieng of the Institute of
Economic Affairs said, “When projects stall due to mismanagement, litigation or
contractor disputes, funds already spent effectively become sunk costs.”
“The loans or bonds that financed them still
require repayment. In effect, Kenya is paying interest on hospitals without
patients, stadiums without spectators, bridges without roads and dams without
water,” they said in an IEA analysis on stalled projects.
Slow progress is also evident in the trade sector.
The Modernisation of the Standards Laboratory
(Legal Metrology Project), launched in July 2020, has achieved only one per
cent completion despite a June 2026 completion target. The project is expected
to cost Sh610 million.
The Warehouse Receipt System, launched in January
2020 to strengthen commodity storage and trading, stands at 22 per cent
completion, with Sh222 million already spent.
Meanwhile, the Commodities Exchange Platform,
launched in 2023 to support structured commodity trading, has reached only 15
per cent completion. The project is expected to cost Sh3.7 billion.
The Warehouse Refurbishment Project under the Kenya
National Trading Corporation stands at 21 per cent completion, even though its
expected completion date of March this year
has already passed.
Agricultural projects aimed at boosting food
production and farmer incomes are also progressing slowly.
The National Edible Oil Crops Promotion Project,
expected to run between 2023 and 2030, has achieved only four per cent
completion so far. The initiative is valued at Sh8.7 billion and is funded
jointly by the government and development partners.
The Kenya Cereals Enhancement Programme – Climate
Resilient Agricultural Livelihoods Window stands at 26 per cent completion
despite receiving both government and donor support.
Meanwhile, the Pyrethrum Industry Recovery Project,
launched in 2014, has reached only 30 per cent completion after more than a
decade. The programme is valued at about Sh3.3 billion.
In the blue economy sector, several maritime
projects are also significantly behind schedule.
The Kenya Lake Victoria Maritime Communication and
Transport Project, valued at Sh3.6 billion, has reached only 15 per cent
completion since its launch in 2023, with Sh555 million already spent.
The Kenya Maritime Data Bank project stands at 14
per cent completion despite its expected completion date of June 2025.
Another initiative, the Maritime Survival Training
and Certification Centre, has reached 28 per cent completion after absorbing
Sh702 million.
Overall, maritime projects valued at more than
Sh5.9 billion have recorded an average physical progress rate of about 19 per
cent.
Infrastructure projects in the aviation sector are
also facing costly delays.
Construction and rehabilitation works at Kakamega,
Kabunde and Migori airstrips have exceeded their original timelines despite
continued funding allocations. The three projects have absorbed more than Sh1.2
billion in public funds.
“The projects utilised 100 per cent of their
mid-year funding despite remaining past their initial expected durations or
lacking updated completion percentages,” Nyakang’o said.
In another case, the purchase of aircraft accident
investigation equipment, which began in July 2020, recorded zero expenditure
during the six-month review period despite having a budget allocation.
Even projects under the Executive Office of the
President have experienced slow implementation.
Modernisation of the Government Press and
refurbishment of buildings, launched in 2013, has reached only eight per cent
completion more than a decade later. The project is estimated to cost Sh1.5
billion.
Refurbishment of Harambee House, which began in
2015, stands at 35 per cent completion and is expected to be finalised this year. Integrity House renovations have also been cited,
being at 36 per cent well past its completion timeline.
Another project involving the Directorate of
Resource Survey and Remote Sensing, launched in 2019, has reached only 22 per
cent completion.
The justice sector is also grappling with delays.
“Mandera Law Courts, whose completion timeline has already lapsed, remained at
13 per cent, indicating significant delays.”
The Uadilifu Case Management project under the
Office of the Director of Public Prosecutions, launched in 2022, has achieved
only 16 per cent completion despite being in its final year.
Nyakang’o warned that persistent delays in capital
project implementation could undermine the effectiveness of public spending and
expose the government to additional costs from litigation and delayed payments.
Instant analysis
As the government continues to prioritise
development spending, the findings raise fresh questions about whether
ministries and implementing agencies have the capacity to deliver projects
within the timelines originally planned.