Auditor General Nancy Gathungu’s September 2025
report scrutinises seven donor-funded electricity transmission line projects
implemented by the Kenya Electricity Transmission Company (Ketraco).
The report has uncovered a web of irregularities, where
at least Sh4 billion in compensation remains unpaid to landowners, while
millions more were squandered through over-payments, fictitious claims, and
blatant violations of procurement and financial laws.
The seven projects, including the high-profile
Ethiopia-Kenya and Kenya-Tanzania power lines, were intended to boost regional
power trade and stabilise the country’s mains grid.
Instead, the audit tells a sad tale of how the very
people meant to benefit from development, the project affected persons (PAPs),
were left in limbo, while public funds vanished in dubious transactions.
The exploitation plays out across all the projects,
putting on the spot the National Land Commission, the implementing agency
Ketraco and the Energy department, as well as the consultancy firms they worked
with in the ventures.
In the Ethiopia-Kenya line, Ketraco paid
Sh8.3 million to seven landowners for parcels of land that were no longer
affected by the final transmission route.
The line had been rerouted, yet the compensation, once
paid, was never recovered. There is no evidence of any effort to reclaim the public funds.
At the same time, dozens of landowners along the
Ethiopia-Kenya line received unexplained second payments, dubbed ‘top-ups’,
totalling Sh24 million.
Gathungu stated that the Resettlement Policy Framework,
the document meant to guide the process, has no provision for such
payments.
The audit could find no justification for the bonus payments.
“lt was therefore not clear why Ketraco made the top-up payments amounting to
Sh24,023,227. In addition, no documentary evidence was provided on any efforts
made by the company to recover the amount.”
In the Nairobi Ring (Suswa-Isinya) line, a 20 per cent
top-up amounting to Sh660 million was added to the initial compensation without
supporting documentary evidence.
Perhaps the most outstanding flaw was that no proper
valuation was conducted on some of the parcels that were compensated.
The audit found that Ketraco and its consultants valued
a tiny, arbitrary sample of land, sometimes as low as five per cent of all
affected parcels, and used these figures to compute compensation for everyone.
In the Ethiopia-Kenya line, only 157 out of 2,638
parcels were physically valued.
The criteria for selecting the samples and the
methodology for extrapolating the values were never provided, opening the door
for massive and untraceable manipulation of figures.
The audit findings on the wayleave compensation
irregularities are part of a broader pattern of infractions in government land acquisition.
This is exemplified in the legal woes of former NLC
Chairman Muhammad Swazuri and his team, who were embroiled in multiple,
multibillion-shilling corruption cases arising from the SGR compensations.
This followed claims of their alleged roles in presiding
over a commission where due process was bypassed, valuations were questionable,
and public funds were paid out irregularly.
Similar concerns have been raised in other key
infrastructure projects, including roads and superhighways.
The sampling fraud in the Ketraco cases had direct
consequences on some of the projects. In the Kenya-Tanzania project, 58 parcels
of land were overvalued by a staggering Sh133 million.
Of the amount, Sh116 million was already paid out to
landowners before the audit uncovered the discrepancy.
In the Olkaria-Lessos-Kisumu line, 19 parcels saw their
compensation irregularly inflated by Sh13.8 million.
In the Kenya-Uganda line, there was an over-payment of
Sh7.7 million to 20 landowners because the actual affected area was less than the
area used for compensation.
The report reveals that the plunder was enabled by a near-total
collapse of oversight, amid reports that the Ketraco board of directors was often
missing in action.
The audit could not find board approval for a Sh105
million payout for community projects in Marsabit county, a sum approved
unilaterally by the managing director.
Crucial documents, among them land scoping reports,
surveyor contracts, valuer agreements, and even title deeds for purchased land,
were consistently “not provided for audit.”
Gathungu says the lack of documentation made it
impossible to verify how land was identified, why certain prices were
negotiated, or whether the billions spent were justified.
“The audit establishes that project conceptualisation
and feasibility assessments were not sufficiently robust to provide reliable
estimates of compensation requirements,” the report states.
The auditor further noted that governance structures
“did not consistently comply with statutory mandates, resulting in weak
oversight.”
In another case, payments were made without acceptance
or agreement. Some Sh17.8 million was paid to 65 PAPs who had rejected offer
letters.
Payment was made without their acceptance and without
executed agreements, contrary to the law. In the Olkaria-Lessos line, Sh314 million
was paid without approved valuations.
Another Sh105 million was approved for community
projects in Marsabit county by the managing director without providing board approval,
contrary to corporate governance rules.
Behind the huge numbers are real Kenyans whose lives
have been seriously affected by the compensation delays.
The audit team, during physical verification, met
landowners who spoke of health complications from transmission lines built too
close to their homes, with one individual claiming the electromagnetic
interference affected a pacemaker.
In other findings, many PAPs signed crop damage reports
without knowing the compensation amount, and were denied any chance to agree or dispute
the valuation.
In the Olkaria-Lessos-Kisumu corridor, trees that were
cut down and paid for have since regrown, now posing a risk of contacting the
live cables.
In what could worsen the situation for the affected
families, funds were co-mingled in Ketraco’s general accounts instead of being
held in protected project accounts.
Some projects, like the Kenya-Tanzania project, four
years behind schedule, is still under construction, with its compensation
process mired in over-payments and underfunding.
The Auditor General wants sanctions against the
concerned individuals, including immediate recovery of all irregular payments.
She has also asked Ketraco to open escrow accounts for
outstanding claims and for disciplinary action against responsible officers.
Gathungu wants Ketraco to “clarify governance roles and
strengthen oversight” and “develop and enforce approved policies, guidelines,
and procedure manuals for wayleave acquisition.”
INSTANT ANALYSIS
As the report lands before the Public Accounts Committee, it presents a critical test for the country’s institutions. Will there
be consequences for what the audit clearly portrays as grand-scale abuse of
public trust and funds? Or will this be another detailed report that gathers
dust, while the same cash cow is milked in the next mega-project? For the
thousands of Kenyans still waiting for compensation, and for taxpayers footing
the bill, the demand for answers and accountability has never been more urgent.