A new report has revealed how
taxpayers’ money is being wasted
on these projects, some of which
were initiated more than 10 years
ago by previous regimes.
Shedding light on the government’s cash crunch, the national
government expenditure report for
the first half of the financial year
indicates the projects have stalled
due to inconsistent or insufficient
funding.
The government ministries, departments and agencies often undertake the projects.
However, some
state agencies did not spend a penny
on development during the entire
six-month period.
“An analysis of the implementation of development projects by
MDAs of the national government
revealed a general delay in project implementation,” the report
by Controller of Budget Margaret
Nyakang’o says.
The report lists several projects
across all the MDAs valued at billions of shillings that have either
stalled or fallen behind schedule.
Completion is in doubt in some
cases.
In the State Department of Roads,
the report lists 10 projects valued at
more than Sh30 billion that have either stalled, fallen behind schedule,
or whose completion is in doubt.
In the sister Department of Transport, Nyakang’o listed another 10
projects valued at more than Sh70
billion whose completion is in
doubt.
This is the case with the State
Department of Lands and Physical
Planning, where the CoB has listed
10 projects valued at more than
Sh74.10 billion, whose completion is doubtful.
“An analysis of the
project implementation status by
the State Department for Lands and Physical Planning revealed general
delay in projects implementation,”
the report reads.
For instance, Kenya Affordable
Housing Finance and Registration
of Community Land, Isiolo South,
projects did not record any expenditure in the first half of financial year
2024-25.
The geo-referencing land parcels
project recorded a completion rate
of 19 per cent, despite the project
starting in July 2013.
In the State Department for Livestock Development, Nyakang’o
listed 10 projects valued at Sh31.42
billion, whose completion is also
problematic.
Out of the 10 projects, four are
already behind their scheduled completion dates.
They are the Livestock Training
Institute Mogotio (yet to start),
Livestock Restocking in Baringo
North (17 per cent complete), establishment of feedlots, fodder and
pasture (27 per cent complete) and the Kenya commercialisation programme (29 per cent complete).
In the State Department of Higher Education, Nyakang’o flagged 10
projects valued at Sh11.98 billion
whose completion is doubtful.
“An analysis of the project implementation status shows delay in
project implementation based on
commencement date and expected
date of completion against the completion rate,” the report reads.
In the State Department for
Housing and Urban Development,
the CoB listed 10 projects valued at
more than Sh86.94 billion.
“An analysis of the project implementation status revealed the State
Department for Housing and Urban
Development spent on three projects only,” the report adds.
Projects that have stalled or whose
completion are in doubt in the
Roads department include the dualling of the Mombasa-Mariakani
Road, which began in July 2023
and is expected to be completed in
January next year.
However, the Sh10.33 billion
project is only 24 per cent complete,
and Sh2.48 billion already has been
spent on it.
The report shows the Sh9.51 billion Wajir-Tarbaj road, which started in January 2023, is only nine per
cent complete.
Its expected completion date
is December next year.
To date,
Sh903.4 million has been spent on
the project.
The Mlango-Benon-State LodgeRiwo Pri-Store-Mto Mbili Road,
whose construction began in April
last year, is only seven per cent complete.
The project is supposed to be
completed next month and has already consumed Sh60 million.
The Chobe-Kambi George-Weru-Matundura and Muti-ini-Thindi
road, whose construction started in
April last year for Sh1.17 billion,
is only nine per cent complete.
The
project, which is supposed to be
completed next month, has already
consumed Sh100 million.
Other doubtful projects are the
Tawa-Nguluni-Itangini road valued at Sh2.40 billion and the Eldas
Township road valued at Sh516.83
million.
Some of the projects whose completion is in doubt in the Transport
department include the revitalisation of the Leseru-Kitale MGR
Branch for Sh.537.42 million.
The project is 75 per cent complete, despite the expected completion date being June last year.
The revitalisation of the Kisumu-Butere MGR Branch line at
Sh575.96 million has also stalled.
The project is 84 per cent complete but was expected to be completed last year. The project has already consumed Sh576 million.
The revitalisation of the Gilgil-Nyahururu MGR Branch line is also
behind schedule.
The Sh1.13 billion
project is 64 per cent complete. The
expected completion date was June
last year.
The Sh5.57 billion Nairobi Bus
Rapid Transport Systems – BRT
Line – that was supposed to be completed in June this year, is only 56
per cent complete. Some Sh1.15 billion has been spent on the project.
Others are the construction of a
new 2.8-kilometre MGR link from
Mombasa SGR Terminus- Miritini MGR station, and the railway
bridge across Makupa Causeway
(completion date June 30, 2024).
Also listed is the construction
of the Access Road to Suswa SGR
Station and to Maai Mahiu SGR
Station (completion date June 30,
2024).
“Measures should be taken to
address the projects implementation challenges by the MDAs to
fast-track the completion of all the
affected multi-year projects whose
completion rates are behind the target timelines,” Nyakang’o said in
the report.
In the State Department of Housing and Urban Development, various Social and Physical Infrastructures under Slum Upgrading valued
at Sh1.3 billion have stalled.
The
project has consumed Sh650 million.
The State Department of Public
Works has stalled the construction
of the Kiwayu Seawall and Jetty
for Sh250 million, the Olekasasi B
Bridge for Sh15.8 million and the
refurbishment of the regional works
office in Kakamega.
The construction of the Kuloko-Masangara footbridge and
the Lusheya-Lubinu footbridge for
Sh14 million each, the Lusheya-Lubinu footbridge for Sh9 million and
Akiriamet Masol footbridge for
Sh16 million have all stagnated.
“An analysis of the projects the
State Department for Public Works
implemented indicated that no projects were funded during the first
half of the financial year 2024-25,”
the report reads.
The State Department for Information Communications Technology and Digital Economy Projects
Implementation, Maintenance and
Rehabilitation of NOFBI Phase II
expansion for Sh11.98 billion has
stalled.
The project, which has already
cost Sh11.13 billion, was supposed
to have been completed in December 2020.
Maintenance and Rehabilitation
of NOFBI Phase II cable for Sh7.81
billion has stalled.
The project was
supposed to have been completed in
2018.
Connectivity to Leather Industrial Park-Kenaine (completion
date 01/12/22) and Construction of
KAIST at Konza Technopolis (completion date 31/12/24) were ongoing as of December 31, 2024, facing
completion date overrun.
“The projects’ implementation
status by the State Department revealed that four development projects had overstretched their target
completion dates, implying delayed
services to the targeted citizenry,”
the report reads.
In the State Department for Energy, the Sh520 million Green Resilient and Expansion Energy Programme project, the Sh78 billion
300MW Suswa Geothermal project
and the Sh4 billion Nuclear Power
Plant Siting are behind their completion timelines.
In the State Department of Water
and Sanitation, the Sh590 million
Tana Water Works Development
Agency is only 10 per cent complete.
The project is supposed to be
completed in June this year
.
“Analysis of project implementation status indicated a low implementation rate for most projects,”
Nyakang’o said.
The Projects Status Analysis of
the State Department for Wildlife
showed that four projects are lagging behind their completion dates.
They include the rehabilitation
of Research and Training Facilities
in Naivasha Headquarters (54 per
cent complete), Construction and
Equipping of Four Research and
Training Centres (78 per cent complete), National Integrated Wildlife
Data Portal (27 per cent complete)
and Combating Wildlife Crime in
Kenya Programme Project-USAID
II (14 per cent complete).