SH16 BILLION

Government to compensate people affected by three road projects

Transport Cabinet Secretary James Macharia said compensation for persons affected by the Eldoret Town by-pass is progressing well.

In Summary

•He told the Senate Standing committee on Roads and Transport that the full compensation in the Eldoret Town Bypass is Sh3.5 billion, which has already been remitted to Kenya National Highways Authority.

•The ongoing projects are the Eldoret Town Bypass, James Gichuru Junction- Rironi Highway and Kibwezi-Athi-Mutomo- Kitui- Migwani Road.

James Gichuru to Rironi road project.
James Gichuru to Rironi road project.

The government will spend over Sh16 billion to compensate people who will be displaced by three major road projects across the country.

The ongoing projects are the Eldoret Town Bypass, James Gichuru Junction- Rironi Highway and Kibwezi-Athi-Mutomo- Kitui- Migwani Road.

Transport Cabinet Secretary James Macharia said compensation for persons affected by the Eldoret Town by-pass is progressing well, and the government has already paid out Sh2.9 billion.

He told the Senate Standing committee on Roads and Transport that the full compensation in the Eldoret Town Bypass is Sh3.5 billion, which has already been remitted to Kenya National Highways Authority.

The Sh2.9 billion was paid to 823 affected persons, who vacated the affected land, he said.

“The contractor has been granted access to 27.296 kilometres of the total right of way of 32 kilometres, which represents 85 per cent of the required wayleave. The remaining 4.7 kilometres should be availed by May 2021,” he said.

Macharia further said the compensation of affected persons by the James Gichuru Junction- Rironi Highway would cost the government Sh10.5 billion.

“In preparation for this exercise, a consolidated compensation schedule amounting to Sh10, 524, 292, 866 was submitted to Kenha by the National Lands Commission,” he said.

The CS however said the schedule was incomplete as it did not include some parcels of land required at Gitaru for the interchange with the Southern and Western bypasses, some structures that were affected partially along the wayleave and some addendums along the road. “The NLC is addressing these issues,” he told the committee.

James Gichuru Junction-Rironi Highway project started in August 2017 and was to be completed within 36 months.

Macharia said Kenha has so far remitted Sh9.7 billion to the NLC for onward payment to the affected persons.

“These payments have in some cases been delayed due to budgetary constraints and family disputes affecting some land parcels,” he said.

The CS further said a compensation schedule amounting to Sh694 million has been submitted to Kenha by the NLC for the compensation of people displaced by the Kibwezi-Athi-Mutomo-Kitui-Migwani Road.

“However, we noted some errors in this schedule, including double compensation and overvaluation of structures. NLC addressed these issues and submitted a revised schedule of Sh1.9 billion in March 2021,” he said.

Macharia said “Kenha is in the process of transferring funds to NLC to facilitate payment to the PAPs”

The Kibwezi-Athi-Mutomo-Kitui-Migwani Road is set to ease traffic flow from Mombasa via Kibwezi, Kitui to Moyale.

Upgrading of the road, which is part of the Northern Corridor Transport Improvement Project, to bitumen standard has been ongoing since August 2017.

Macharia said they have been making compensation based on the availability of funds.

“If we wait to get all the money for us to embark on compensation, then this project may collapse,” he explained.

 

Edited by Kiilu Damaris

WATCH: The latest videos from the Star